Save Ocean Beach

The natural and physical resources of Ocean beach and its adjacent City Dunedin are under threat and you can help!

Seawall work after summer | Otago Daily Times Online News : Otago, South Island, New Zealand & International News


Work to remove a damaged seawall ramp and stairs at the Esplanade at St Clair and construction of replacement beach access will not take place before the summer.
Dunedin city council transportation policy engineer Pieter Besuijen said staff had decided it would make more sense to dismantle the stairs and ramp at the same time as work on installing new access was done.
The stairs and ramp were closed permanently in September last year, after being repaired multiple times following damage from high seas.
The intention had been to remove the damaged stairs and ramp before summer, but it was decided it would be cheaper to do all the work together, as part of one contract, Mr Besuijen said.
The council did not want to do the work over the summer when the area was busy, as it would require the use of a crane and other heavy machinery.
The design and exact location of the new access was not yet decided, as the council was waiting on information from the Ministry of Business, Innovation and Employment. However, it was expected the work would begin after summer and would be done before July next year.
The council reached a confidential agreement with engineering firm CPG in August, after the firm, which merged with the firm that designed the stairs and ramp, did not initially accept liability for their continued failing.
The council has budgeted $130,000 for the work this financial year.

Sea wall settlement confidential | Otago Daily Times Online News : Otago, South Island, New Zealand & International News

The Dunedin City Council and engineering consultants CPG have reached a settlement on who is responsible for the replacement of damaged sea wall ramp and stairs at St Clair.

However, part of the agreement was that details of it remained confidential, infrastructure services committee chairman Cr Andrew Noone said.
The council signed off the settlement at its last meeting, in August.
The council and and CPG are now discussing options and designs for new access to the beach.
The city council believed the stairs and ramps from the Esplanade at St Clair to the beach failed several times - most recently last September - because of a combination of construction and design faults.
Design consultant Duffill Watts and King and construction company Naylor Love agreed to strengthen and repair the ramp and stairs at no cost to the council, and facilities were replaced in 2007.
Duffill Watts and King had since merged with CPG and CPG had not accepted liability for subsequent failings.
Council transportation operations manager Graeme Hamilton said a settlement had been reached between the parties in August, and while "the ink was still drying", he described it as a "better than 90% agreement".
The council had allocated $130,000 in its 2012-13 budget for replacing the beach access at the Esplanade.
Mr Hamilton said things were now moving in a "favourable and progressive" direction, and a meeting to develop design options was held yesterday.
There were several ideas on the table about the best beach access and location, which were what the parties were starting to work through.
It was unclear how long it would be before there would be any decision about the access or when the work would be completed.
-debbie.porteous@odt.co.nz

DCC optimistic of sea wall deal with company | Otago Daily Times Online News : Otago, South Island, New Zealand & International News


Dunedin City Council staff are to meet the company it believes responsible for a failed ramp and steps on the sea wall at St Clair, optimistic a settlement can be negotiated this month.
Any resolution is also expected to include a decision on new access to the beach.
Early this year, a report to the council said the sea wall had failed to gain a code of compliance certificate when it was completed in 2004, mainly because of concerns over the durability of a ramp and stairs leading from the Esplanade to the beach.
Since then, the ramp and stairs have been damaged in heavy seas six times, most recently in September last year when they were closed after concrete cracked, exposing steel reinforcing rods.
A council report after incidents in 2004 and 2005 found failures then were caused by a combination of construction and design faults.
Design consultant Duffill Watts and King and construction company Naylor Love agreed to strengthen and repair the ramp and staircase at no cost to the council, and the facilities were replaced in 2007.
The most recent damage appears to be in the same area, materials used to reinforce the ramp having failed.
Duffill Watts and King has merged with the firm CPG, which has not accepted liability for the failings.
The council is seeking resolution through a settlement, rather than court action, while also working with the company on redesigning the sea wall's steps and ramps.
Council transportation operations manager Graeme Hamilton said councillors were updated on progress last week, in a non-public part of the infrastructure services committee meeting.
He could not discuss details, saying he did not want to prejudice the outcome of the meeting, but said council staff would discuss "everything" with CPG at a meeting in mid-August.
The council has previously said the existing ramp and some of the existing stairs would be removed and a new set of stairs built at the St Clair Salt Water Pool end of the sea wall, but Mr Hamilton would not confirm that yesterday, other than to say design, location and a timeframe would be discussed at the meeting.
The council has tagged $250,000 for the beach access project this financial year.
He was "always optimistic" a resolution could be reached with CPG, he said.
"It's [the meeting's] a positive move forward, to resolve what has been a difficult issue."

Erosion-plan vote next week | Otago Daily Times Online News : Otago, South Island, New Zealand & International News

Dunedin city councillors will decide next week whether to back a plan to continue a holding pattern in the battle against erosion in the Ocean Beach Domain area for the next decade.
In the meantime, staff would do the costed design work on what are considered to be the two most viable medium- to long-term ways to manage erosion in the area - a buried backstop wall 10m inland and/or a 30m managed retreat of the dunes.
Work on developing a long-term plan for the coastal area between St Clair and Lawyers Head began after severe storms caused significant erosion in the area in 2007.
The council has continued to battle erosion on the stretch, using sand replenishment and other minor work.
A report from consultants Tonkin and Taylor, commissioned in 2010, suggested the long-term "adaptive management approach" now being recommended to council following public consultation.
The council received 26 submissions on the report, offering mixed views on how to proceed.
Some submitters clearly favoured a managed retreat at Middle Beach, but the hearings committee considering submissions concluded a buried wall and a retreat were both viable options and data collection over the next five years would confirm which option was then considered most appropriate.
Councillors will consider a report containing recommendations from the hearings committee and council parks manager Lisa Wheeler at Monday's community development meeting.
The report recommends the council continue sand replenishment and other minor work alongside careful monitoring of the area for up to 10 years, at an expected to cost of $4 million to $8 million.
A buried backstop wall 10m back from the 2007 dune toe position should be designed and costed in the meantime, for intended installation between the end of the St Clair seawall and the cultural centre in 10 to 50 years' time, but earlier if required.
A continuation of the buried wall along Middle Beach to the St Kilda Surf Club should also be designed and costed, as should a managed retreat based on a 30m setback from the 2007 dune toe.
Ms Wheeler said sports fields at Kettle Park would not be substantially affected by a buried wall, other than during its construction, but a managed retreat would have a significant effect on the fields, which would become part of the dune area.
The fields were fine in the meantime, and clubs would be consulted if monitoring showed that had changed, she said.
Initial estimates put the cost of an inland wall at $8 million to $13 million, or $11 million to $19 million for a managed retreat, including the cost of cleaning up a historic landfill under Kettle Park, the report said.

Erosion-plan vote next week

News: Dunedin

Dunedin city councillors will decide next week whether to back a plan to continue a holding pattern in the battle against erosion in the Ocean Beach Domain area for the next decade.In the meantime, staff would do the costed design work on what are considered to be the two most viable medium- to long-term ways to manage erosion in the area - a buried backstop wall 10m inland and/or a 30m managed retreat of the dunes.
Work on developing a long-term plan for the coastal area between St Clair and Lawyers Head began after severe storms caused significant erosion in the area in 2007.
The council has continued to battle erosion on the stretch, using sand replenishment and other minor work.
A report from consultants Tonkin and Taylor, commissioned in 2010, suggested the long-term "adaptive management approach" now being recommended to council following public consultation.
The council received 26 submissions on the report, offering mixed views on how to proceed.
Some submitters clearly favoured a managed retreat at Middle Beach, but the hearings committee considering submissions concluded a buried wall and a retreat were both viable options and data collection over the next five years would confirm which option was then considered most appropriate.
Councillors will consider a report containing recommendations from the hearings committee and council parks manager Lisa Wheeler at Monday's community development meeting.
The report recommends the council continue sand replenishment and other minor work alongside careful monitoring of the area for up to 10 years, at an expected to cost of $4 million to $8 million.
A buried backstop wall 10m back from the 2007 dune toe position should be designed and costed in the meantime, for intended installation between the end of the St Clair seawall and the cultural centre in 10 to 50 years' time, but earlier if required.
A continuation of the buried wall along Middle Beach to the St Kilda Surf Club should also be designed and costed, as should a managed retreat based on a 30m setback from the 2007 dune toe.
Ms Wheeler said sports fields at Kettle Park would not be substantially affected by a buried wall, other than during its construction, but a managed retreat would have a significant effect on the fields, which would become part of the dune area.
The fields were fine in the meantime, and clubs would be consulted if monitoring showed that had changed, she said.
Initial estimates put the cost of an inland wall at $8 million to $13 million, or $11 million to $19 million for a managed retreat, including the cost of cleaning up a historic landfill under Kettle Park, the report said.


DCC mulls options as erosion closes beach track

Photo by Craig Baxter
Photo by Craig Baxter
Dunedin City Council sportsfields and facilities officer Harold Driver looks at erosion on the walkway between St Clair and St Kilda Beaches which forced the closure of the track last week.
Council staff and consultants met on site yesterday morning to determine what repairs were required.
Parks and reserves team leader Lisa Wheeler said part of the track had been narrowed and an 80m realignment would "hopefully" be in place by the end of the week.
She said the council would eventually decide whether the realignment would become permanent, or the original track repaired.
"We will wait until the weather calms down a bit and if it's worth doing repairs there, then we will."
The council's position on the erosion meant monitoring and replenishment work was being carried out as required, but major work to protect the area would not occur for another decade.
However, "one of the goals that we are trying to achieve is maintaining that recreation flow through there", Ms Wheeler said.
Signs notifying the public of the realignment would be erected today.


Warning on beach scheme

 68  0 ShareThis
Mike Hilton
Mike Hilton
The Dunedin City Council's luck could run out if severe storms force it to bring forward millions of dollars worth of erosion protection work planned for Ocean Beach, a hearings committee has been told.
The warning came from University of Otago coastal processes specialist Dr Mike Hilton yesterday, as the council's Ocean Beach hearings committee backed plans for a holding pattern in the area for the next decade.
The holding pattern would include beach monitoring and replenishment work as required, and could cost up to $8 million over the decade.
It was to be followed by even more expensive work to protect the area, including a buried backstop wall, managed retreat and clean-up of an old landfill under Kettle Park.
The options - covering the area from St Clair to Lawyers Head - were detailed in a report by Tonkin and Taylor, which led to public consultation and yesterday's deliberations.
However, Dr Hilton told the meeting yesterday the timeframes for when the work would be required remained uncertain, and could be "quite wrong" if more severe weather struck.
The margin of error east of the St Clair sea wall was "quite small", with protective sand sausages already exposed by the elements, he said.
The council had been "quite lucky" since severe storms in 2007 led to emergency repairs and prompted the start of the planning process for the future management of Ocean Beach.
However, another severe weather event could force the council's hand at any time.
"We could be very unlucky at any time," Dr Hilton said.
Richard Reinen-Hamill, the author of the Tonlin and Taylor report, agreed, saying the work timeframes in his report were "just predictions".
"We are dealing with uncertainty and trying to manage uncertainty." However, the prospect of a sudden bill for major work would also be "problematic" for the council, given present financial constraints, council community and recreation services manager Mick Reece told the meeting.
"Paying for it in the next financial year has never been an option," he said.
The discussion came as councillors endorsed recommendations contained in the report, beginning with the holding pattern over the next decade costing up to $8 million.
That was to be followed by construction of an expensive buried backstop wall, costing up to $3 million, inland from the sand dunes, stretching 300m east from the end of the existing St Clair sea wall. Elsewhere, the report recommended a managed retreat along a 1km front at Middle Beach, allowing the sea to reclaim parts of Kettle Park, or a second buried backstop wall to protect the playing fields.
A managed retreat would cost up to $16 million, as a historic landfill under the playing fields would need to be cleaned up, while a second buried backstop wall could cost $10 million.
The committee yesterday endorsed plans for the managed retreat at Middle Beach, but chairman Cr Colin Weatherall stressed that did not mean the area was being abandoned, although some Kettle Park playing fields would be lost.
Council parks manager Lisa Wheeler said the council would work with the Dunedin Rugby Football Club - which used the park - to accommodate its needs as part of a wider review of sportsfield capacity.
Also yesterday, committee member Cr Bill Acklin questioned whether it would be better to bring forward work on the buried backstop wall and managed retreat.
That would allow funding of $250,000 a year - included in the council's draft long-term plan for the next decade - to be used to offset loan servicing costs to pay for the major work, he suggested.
However, Mr Reece said the annual sum in the draft budget was a contingency fund, and might not need to be spent from year to year.
Delaying the work by up to a decade would also allow more data to be collected, helping shape the best options to protect the coastline.
It was possible work could be brought forward when the council's financial position was "more favourable", and work on consents and designs could begin in the meantime, he said.
Following the deliberations, committee chairman Cr Colin Weatherall asked staff to report back in June with recommendations.


By Chris Morris on Thu, 5 Jan 2012
News: Dunedin | DCC


A public hearing next month will help decide what to do about erosion problems threatening Dunedin's Middle Beach.

The Dunedin City Council has been investigating the problems, and what to do about them, since severe storms in 2007 first highlighted the threat of erosion to Kettle Park and other facilities in the area.

That resulted in a draft Ocean Beach management plan prepared by consultant Tonkin and Taylor last year, covering a 4km area stretching from St Clair to Lawyers Head.

The draft plan recommended continuing the council's holding pattern of monitoring and sand-replenishment work - put in place after the 2007 storms - in the meantime.

However, the report also canvassed 13 longer-term options and recommended a managed retreat from Middle Beach and Kettle Park, or construction of an inland buried backstop wall to protect the area over the next 10 to 50 years, at an initial estimated cost of between $8 million and $19 million.

Yesterday, council community and recreation services manager Mick Reece said public consultation on the draft plan had prompted 17 submissions, including input from the Department of Conservation and individuals.


About half supported the draft plan's recommendations, while the rest had mixed views, he said.

A public hearing, set down for February 21 to 23, would be held to help determine a way forward, Mr Reece said.

chris.morris@odt.co.nz

A clay cap stretching 150m on top of sand dunes at Dunedin's Middle Beach has been removed by Dunedin City Council contractors, amid concerns further erosion could have caused it to collapse. Photo by Craig Baxter.
A clay cap stretching 150m on top of sand dunes at Dunedin's Middle Beach has been removed by Dunedin City Council contractors, amid concerns further erosion could have caused it to collapse. Photo by Craig Baxter.

As waves continue to erode Dunedin's Middle Beach, major excavations have been carried out in recent weeks to remove a clay cap covering sand dunes, which was at risk of collapse.
Dunedin City Council staff yesterday confirmed a clay cap stretching about 150m along the top of dunes at Middle Beach had been removed by contractors, amid fears it was being undermined by waves.
Parts of the cap had already fallen away, leaving plant roots exposed and the remaining cap at risk of collapsing on to the beach below, council parks manager Lisa Wheeler said.
Instead, the cap - up to 1m deep in places - and vegetation in the area was removed by council contractors last month, leaving a flat shelf, she said.
The clay was then replaced with about 7000cu m of sand dredged from Otago Harbour, to restore some of the top of the dunes, Mrs Wheeler said.
"When we took the clay capping off, it was just a flat shelf. We've actually brought the sand back on to try and build the dune back up again.
"It was quite significant [work]," she said.
Otago Regional Council consents required the city council to collect any clay falling on to beach, to prevent it being washed into the marine environment, she said.
The work was undertaken as a "precautionary" measure to avoid that, at a cost of $70,000, but also to ensure public safety for beach-goers, she said.
Public access to the dunes was already restricted, with the area above fenced off since it was discovered the dunes were contaminated by material from a historic landfill located under nearby Kettle Park.
However, plants left leaning over after parts of the cap collapsed were adding to the pressure on the shelf, Mrs Wheeler said.
"Some of it had [collapsed], and there were big cracks where even the pressure of just someone standing on it was moving some other areas of it.
"You just need another little bit of imbalance and it all would have just gone."
Council community and recreation services manager Mick Reece said the clay had been placed on top of the dunes "years ago" - although the exact date was not known - to help promote plant growth.
Adding the clay was "not a good move, as we now know", and would have had to be removed regardless of what decisions were made about the long-term future of Middle Beach.
"As the face of the dune was tested in any way by the weather, you have this great big pie crust on the top that if it was undercut at all, the whole thing collapsed, like slabs of clay down on to the beach.
"Whatever happens in the future ... that clay had to go anyway."

Blog Archive